State Streets Pavement Rehabilitation Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Update January 8, 2025

Happy New Year! The State Streets Road Rehabilitation Project is back in full swing as crews resumed work on January 6, 2025.

This week, construction is focused on completing all remaining curb and gutter installations along Vermont Avenue. Work includes:

  • Both sides of Vermont Avenue South, from 19th Street to Stone Boulevard.
  • The west side of Vermont Avenue, from Jefferson Boulevard to 17th Street.

Looking ahead to next week, crews will begin work on Carolina Avenue and 19th Street, with concrete pouring scheduled from Wednesday through Friday.

Please note that all scheduled work is subject to weather conditions. Crews will monitor conditions closely to ensure safety and efficiency while making any necessary adjustments to the schedule.

Thank you for your continued support. Stay tuned for more updates as the work progresses!

Phase 1 - State Streets Pavement Rehabilitation Project

Map of Phase 1:  Winter work curb and gutter (purple), and curb ramps (blue)

State Streets Rehabilitation Map 10.3.23 

  Map of State Streets Infrastructure Projects

Status:

Construction

 

Location:

The bounds of this Project will be within Stone Blvd, Park Blvd, 15th St, and Jefferson Blvd (Project Map)

 

Background: 

The state streets neighborhood underwent sewer rehabilitation in 2020 and a water main improvement in 2021. The pavement condition in this neighborhood is poor.   

The objective of the State Streets Infrastructure Projects is to correct some of the infrastructure deficiencies identified in the City’s Sewer Master Plan (State Streets Sewer Project),  Water Master Plan Water Master Plan (State Streets Water Main Replacement Project), and Pavement Management Plan.

 

Description: 

This project will consist of  road rehabilitation and striping, adding ADA ramps, and fixing curbs and gutters. This project will improve the condition and quality of the road, striping, curb and gutter. This will improve the conditions for active transportation.  

  

Schedule: 

Design Early 2024

Constructability Review April 2024

Bid Closed July2024

Construction Contract Awarded to George Reed August 21, 2024

Ceremonial Ground Breaking at Willie DaPrato Park September 12, 2024 

Constriction Notice to Proceed Issued October 21, 2024

- Winter work will include curb, gutter, valley gutters, and curb ramps.

- Schedule is dependent on weather

Road Rehabilitation Anticipated to start April 1, 2025

- This will be dependent on weather.

 

Construction Cost: 

$6.7 Million  

 

Funding: 

SB1: The Road Repair and Accountability Act of 2017  

Measure E 

 

Door Hangers distributed February 13-15, 2024:

Door Hanger February 2024 English

Door Hanger February 2024 Spanish

Door Hanger February 2024 Russian

 

Letter Mailed October 15, 2024:

Letter Mailed October 2024 English

 

Consultant(s): 

Bennett Engineering - Design - Approved July 19, 2023

George Reed - Construction - Approved August 21, 2024

FAQs

Can a pothole be fixed before then?
When will the street be fixed?
Can this project fix the sidewalks?

Past Project Updates

October 23, 2024
November 6, 2024
November 13, 2024
November 27, 2024
December 13, 2024
December 20, 2024

 

Contact: 

Bridget McGinnis 

Project Engineer 

Assistant Engineer, Capital Project

(916) 617-5033 

 